We are now approaching the point in construction where we need to tie in the new road to the existing road.
This will be achieved over five phases detailed below. This will involve Traffic Management and three way and two-way lights to provide a safe working area to complete the tie in.
Phase 1 – 3-way lights on junction (2 days only) 10th & 11th Sept 2021 tying in the southern arm onto Hay Lane.
Phase 2 & 3 – 2-way light at garden centre from 13th Sept 2021 for approx. 5 weeks, tying in the northern and eastern arms to Hay Lane and Wharf Road respectively.
Phase 4 – 2-way lights for 3 days 8th to 10th November, closing off Hay Lane and Wharf Road sections and tying in the new road sections. We still need lights for carrying out kerbing on Hay Lane, which will be from 10th November to 19th November. This includes an additional drainage section on Hay Lane South.
Phase 5 – Night Time Road closures to do final surfacing and lining works for 3 nights from 8PM – 6AM Wednesday to Friday 17th, 18th, & 19th November. This work is weather dependant and is subject to change.
Rather than try and add these Phase drawings on this newsletter, please click on the highlighted Phases below to be taken to the drawings loaded on our website which will give a better view.
All premises access will be maintained at all times.